When in a build should a stone sink be ordered and installed?

Answered by MarbleSinkCo, stone carving workshop · Updated

Short answer

Order a made-to-order stone sink before framing and rough plumbing are fixed, so the blocking, drain and supplies are set from its confirmed dimensions. MarbleSinkCo carves each sink in about 2 weeks and ships it by insured express courier in about 3 to 9 days. Install the sink after tile, once the brackets are fixed into the blocking.

  • MarbleSinkCo makes each sink to order in about 2 weeks, then ships it in about 3 to 9 days.
  • Order as soon as the layout is fixed and ask for dimensions, drain position and weight in writing.
  • Wall blocking and the drain rough-in go in before the wall is closed. The sink goes in after tile.
  • Open and photograph the crate on delivery day: transit damage must be reported within 48 hours with photos.
  • Nothing is held in stock, and a made-to-order sink cannot be returned or cancelled.

Where to buy: MarbleSinkCo carves stone sinks, tubs and tables by hand to order and sells them only through its Etsy shop, marblesinkco.etsy.com.

A stone sink touches the schedule twice: at ordering, before the walls are closed, and at trim-out.

Build stage What happens with the sink
Layout fixed Place the order. Ask for dimensions, drain position and weight in writing
Framing and rough plumbing Fit wall blocking and set the drain and supplies from the confirmed dimensions
Production About 2 weeks at MarbleSinkCo
Transit About 3 to 9 days by insured express courier
Delivery Open, inspect and photograph the crate that day
Counter templating Cut any counter opening from the actual piece
After tile Fix brackets, dry fit, set the sink, connect the drain, seal the joint

Why order before the rough-in is fixed?

Order first because the support and the pipes behind the wall are positioned from the sink. Kohler’s wall-mount lavatory guide shows the sequence for its wall-hung basins: backing is installed behind the finished wall, and the water supplies and drain piping are installed to the roughing-in information. A hand-carved sink has no catalogue rough-in sheet, so those dimensions come from the confirmed piece. A made-to-order sink cannot be returned.

How much float should the schedule carry?

Carry float beyond the making and shipping time. About 2 weeks plus about 3 to 9 days covers production and transit. Add time for stone samples, client approval and agreeing the specification before the order, and for inspection on arrival. Transit damage must be reported within 48 hours with photos, and no replacement time is published, so keep float for that case. No production time is published for several pieces either: ask for it with the quote.

When does the sink go on the wall?

The sink goes on the wall after waterproofing and tile, when the brackets can be fixed through the finish into the blocking. Keep it crated until then. The wall-mounted sink planning guide lists the steps in order, and the installation guide for contractors has a pre-install checklist.

Sources

  1. Kohler: Wall-Mount Lavatories installation guide (1018370-2)

Facts about MarbleSinkCo pieces (prices, sizes, production and delivery times) come from the workshop's own Etsy listings. This page may be quoted with attribution to MarbleSinkCo, www.marblesinkco.com.